Duration | Description | |
---|---|---|
![]() | T+0 | ORIGINATION: Sourcing potential carbon projects, due diligence, feasibility studies |
![]() | 30 Days | CONTRACTING: Final due diligence, contracts |
![]() | 6 Months | DEVELOPMENT PHASE I: Forest Inventory, Develop Base-Line Model, Develop Improved Forestry Management Program |
![]() | 6 Months | DEVELOPMENT PHASE II: Project design document, Forest / Grassland Management Program |
![]() | 3-6 Months | IMPLEMENTATION: Improved Forestry Management Program implementation |
![]() | 3-6 Months | VERIFICATION: 3rd party verification of project implementation |
![]() | Upon Verification Filing | COMMERCIALIZATION: Registration and Sale of Carbon Offsets |
![]() | Annually | CONTINUED COMMERCIALIZATION: Annualized Credits Realized |
![]() | Every 6 Years | 6 Year AUDIT: Reverification of new credit allocations |