Estimated Project Timeline

DurationDescription
T+0ORIGINATION: Sourcing potential carbon projects, due diligence, feasibility studies
30 DaysCONTRACTING: Final due diligence, contracts
6 MonthsDEVELOPMENT PHASE I: Forest Inventory, Develop Base-Line Model, Develop Improved Forestry Management Program
6 MonthsDEVELOPMENT PHASE II: Project design document, Forest / Grassland Management Program
3-6 MonthsIMPLEMENTATION: Improved Forestry Management Program implementation
3-6 MonthsVERIFICATION: 3rd party verification of project implementation
Upon Verification FilingCOMMERCIALIZATION: Registration and Sale of Carbon Offsets
AnnuallyCONTINUED COMMERCIALIZATION: Annualized
Credits Realized
Every 6 Years6 Year AUDIT: Reverification of new credit allocations